PROJECT: ARC Timber Jetty, Colwyn Bay, North Wales
CLIENT: ARC Aggregates
DESIGNER: Quadriga
CONTRACT OVERVIEW: Replacement of cross bracing to jetty piles in greenheart timber

SCOPE OF WORKS:
Provision of bird cage scaffold hung from jetty platform.
Delivery and floatation of 6m long x 300mm x 200mm greenheart timber members.
Erection of lifting equipment in order to position the members between jetty piles.
Drilling by hand auger and bolting of end fixings.
STATUS: Principal contractor
VALUE: £45k
DURATION: 3 summers (working within a 12 week tide window each year)
CONTACT US : info@quadrigaltd.com 0808 100 37777 or 01606 330888
Previous page: Contact Us
Reconstituted Stone | Terracotta and Faience Restoration | Timber Repair | Epoxy Resin Injection
Concrete Repair | Structural Repair | Waterproof Deck Membranes | Damp Proofing
Basement Waterproofing (Tanking Membranes) | Pest Control | Helifix | K-grip
Car Park Refurbishment