| PROJECT: Chorlton Street NCP, Manchester
CLIENT: NML
PLANNING SUPERVISOR: Oscar Faber Consulting Ltd
CONTRACT OVERVIEW: Total car park refurbishment to four car decks with ground floor bus station.
SCOPE OF WORKS:
- Concrete repairs to decks and ramps, columns and soffits
- Resin Injection to fractures
- Total redecoration of concrete structure including columns, walls and soffits
- Replacement of defective expansion joints
- Installation of mechanical joints
- Repairs to defective asphalt membrane
- White thermoplastic lining
- New illuminated signage throughout
- Installation of six camera CCTV surveillance system
- Installation of new Armco crash barriers
- Strengthening of existing crash barriers
- Installation of structural steel support frame to bus station soffit
- Total rewire of all decks including lighting, pay-on-entry systems and CCTV
- Construction of customer services center within car park
- Introduction of pay-on-entry and automatic exit/entry barriers
- Introduction of CCTV security system
- Staircase modifications
- External façade cleaning
STATUS: Principal contractor
VALUE: £950k
DURATION: 26 weeks
|