| PROJECT: Shipley Art Gallery
CLIENT: Metropolitan Borough Council of Gateshead
PLANNING SUPERVISOR: Development & Enterprise Council of Gateshead
CONTRACT OVERVIEW: Stone and masonry restoration, cleaning and re-pointing
SCOPE OF WORKS:
- Removed all defective cast iron down pipe and repaired ornate hoppers.
- Cleaned stonework to remove algae growth.
- Replaced over 250 stone balusters.
- Replaced coping cramps in stainless steel.
- Repaired other items of stonework such as coping stones and parapet stonework.
- Re-pointed stonework and brickwork generally using hydraulic lime mortar.
- Carried out repairs to lead flashings.
STATUS: Principal contractor
VALUE: £125k
DURATION: 3 months
|