| PROJECT: Nantwich War Memorial
CLIENT: BDS Consultants
SUPERVISOR: Crewe and Nantwich Council
CONTRACT OVERVIEW: Stabilisation and stone refurbishment of memorial
SCOPE OF WORKS:
- Erected a boarding around statue to protect against unauthorised access.
- Excavated trial pits around the monument to see what the soil was built up from.
- Scaffolding was then erected around the statue to protect from any further movement
- A company called Uretech injected liquid foam into the ground and the foundations of the monument to establish it and reposition the statue in an upright position.
- Upon completion of this work, the paving stones around the monument were replaced and a high pressure wash was used to clean the statue.
STATUS: Principal contractor
VALUE: £8k
DURATION: 2 weeks
|