| PROJECT: The British Museum, London WC1
CLIENT: The Trustees of the British Museum
DESIGNER: Frank Timothy Associates
ENGINEERS: John Mason & Partners
CONTRACT OVERVIEW: The stabilisation of the North Pediment
SCOPE OF WORKS:
- Diamond core drilling down to 2.5m deep
- Design and placing of epoxy resin grout
- Supply and installation of stainless steel bars, plates and tie bars
- Load testing of all anchorages
STATUS: Sub contractor to HBG Construction
VALUE: £34k
DURATION: 4 weeks
|