| PROJECT: 201 Deansgate, Manchester
CLIENT: Waterman BBT
PLANNING SUPERVISOR: Stephen Southwick
CONTRACT OVERVIEW: Structural repairs to building
SCOPE OF WORKS:
- Project to repair damaged brickwork.
- Investigation and repair of the horizontal expansion joints on the 2nd and 4th floor of the building, as they were not functioning properly.
- Loose or missing bolts fixing support bracket to edge of concrete floor slab.
- Misaligned or missing serrated washers
- Increased cavity widths
- Weep holes in brickwork leaf above cavity tray not formed.
- Cavity above cavity tray blocked with mortar debris
- Reduced bearing of brickwork onto masonry support angle due ti increased cavity widths
STATUS: December 2004
VALUE: £350k
DURATION: 8 months
|