| PROJECT: Natwest Bank, Ruthin, Wales
CLIENT: Davies & Son Ltd
CONTRACT OVERVIEW: Timber repair and consolidation
SCOPE OF WORKS:
- South Gable Elevation of the above establishment
- Drill 8mm diameter holes at 100-120mm centres along the grain.
- For timbers wider than 100mm across the accessible face, additional holes will be drilled at 50mm from the centre row, at staggered 120mm centres.
- Inject Boron Ultra 78 Paste in pre-drilled holes.
- For timbers prone to re-wetting or in continuous damp, Boron Ultra Rods will be inserted in each hole to provide a long term reservoir.
- Remove all debris into appropriately marked locations ensuring compliance with ‘Duty of Care’ regulations.
STATUS: Principal contractor
VALUE: £2.9k
DURATION: 4 days
|