Chorlton Street NCP

Project : Idelwells Shopping Centre
Project : Westmoreland Shopping Centre MSCP
Project : Arndale Centre MSCP
Project : Newbridge Street NCP
Project : Chorlton Street NCP
PROJECT: Chorlton Street NCP, Manchester
CLIENT: NML
PLANNING SUPERVISOR: Oscar Faber Consulting Ltd
CONTRACT OVERVIEW: Total car park refurbishment to four car decks with ground floor bus station.
SCOPE OF WORKS:
Concrete repairs to decks and ramps, columns and soffits
Resin Injection to fractures
Total redecoration of concrete structure including columns, walls and soffits
Replacement of defective expansion joints
Installation of mechanical joints
Repairs to defective asphalt membrane
White thermoplastic lining
New illuminated signage throughout
Installation of six camera CCTV surveillance system
Installation of new Armco crash barriers
Strengthening of existing crash barriers
Installation of structural steel support frame to bus station soffit
Total rewire of all decks including lighting, pay-on-entry systems and CCTV
Construction of customer services center within car park
Introduction of pay-on-entry and automatic exit/entry barriers
Introduction of CCTV security system
Staircase modifications
External façade cleaning
STATUS: Principal contractor
VALUE: £950k
DURATION: 26 weeks
Previous page: Contact Us
Reconstituted Stone | Terracotta and Faience Restoration | Timber Repair | Epoxy Resin Injection
Concrete Repair | Structural Repair | Waterproof Deck Membranes | Damp Proofing
Basement Waterproofing (Tanking Membranes) | Pest Control | Helifix | K-grip
Car Park Refurbishment