Mitford Castle
Project : St Mary The Virgin Church, Eton Bray
Project : Cornet Castle, Guernsey

In recent discussions with Shepherd Offshore Plc the owners of the land/ruin , Cyril Winskell, Consultant Architect and representatives from English Heritage, the following work will be carried out in 2004 to arrest some of the ongoing deterioration of the structures.
Stonework Consolidation and Repair - Phase 1
• Central Section : West Curtain Wall
• Northern Section : West Curtain Wall
SCOPE OF WORKS:
• Erect fully boarded working lift scaffold without physical ties into the structure
• Removal of vegetative growth deep rooted into masonry
• Repair exposed core stonework by rough backing
• Repair coursed ashlar by raking joints and repointing
• Treat delaminating stonework with consolidation fluids
• Gravity feed masonry consolidation to core works using Pozzolanic cement grouts.
• Attend archaeologists watching brief
STATUS: Main Contractor
Phase II - IV - £1M
Previous page: Contact Us
Reconstituted Stone | Terracotta and Faience Restoration | Timber Repair | Epoxy Resin Injection
Concrete Repair | Structural Repair | Waterproof Deck Membranes | Damp Proofing
Basement Waterproofing (Tanking Membranes) | Pest Control | Helifix | K-grip
Car Park Refurbishment