PROJECT: Newbridge Street NCP, Newcastle

CLIENT: NCP Ltd

PLANNING SUPERVISOR: Hill Cannon

CONTRACT OVERVIEW: Total car park refurbishment

SCOPE OF WORKS:

  • Installation of structural steelwork of soffit of car park

  • Access was gained by mobile access platforms

  • Cheaper plates at basement level were removed

  • Various concrete repairs to decks were carried out

  • Also beams over entrance and exist ramps were repaired

  • All soffits were scarped down

  • New fairing coat anti-carbonation coating applied to front façade

STATUS: Principal contractor
VALUE: £64k
DURATION: 8 weeks


Previous page: Contact Us




Masonry Repair   |   Brickwork Repair   |   Stone Restoration   |   Marble and Terrazzo Restoration
Reconstituted Stone   |   Terracotta and Faience Restoration   |   Timber Repair   |   Epoxy Resin Injection
Concrete Repair   |   Structural Repair   |   Waterproof Deck Membranes   |   Damp Proofing
Basement Waterproofing (Tanking Membranes)   |   Pest Control   |   Helifix   |   K-grip
Car Park Refurbishment