PROJECT: Newcastle Crown Court
CLIENT: Rotary Yorkshire Ltd
PLANNING SUPERVISOR: Mr. Martin Bailey
CONTRACT OVERVIEW: Upgrading of the electrical infrastructure and installation of data cabling networks to allow The Court Service to install IT equipment to facilitate the implementation of the Courts and Tribunals Modernisation Programme.

SCOPE OF WORKS:
Removal of redundant electrical installation.
Removal of redundant data network.
Supply, install, test and commission new small power circuits.
Supply, install, test and commission new Cat 5e data cabling and associated patching frames and patching panels.
Modify the existing fire alarm systems.
Modift the existing alarm systems and an ancillary services.
Supply, install, balance, test and commission the building services installations.
All necessary repairs to court rooms.
STATUS: Complete
VALUE: £400k
DURATION: 30 weeks
Previous page: Contact Us
Reconstituted Stone | Terracotta and Faience Restoration | Timber Repair | Epoxy Resin Injection
Concrete Repair | Structural Repair | Waterproof Deck Membranes | Damp Proofing
Basement Waterproofing (Tanking Membranes) | Pest Control | Helifix | K-grip
Car Park Refurbishment