PROJECT: St. Anne's Church, Hindford
CLIENT: WDI Properties
CONTRACT OVERVIEW: Helifix installallation
SCOPE OF WORKS:
Gain access to area of work via scaffold.
Relevant COSHH assessments to be consulted before any repair products are used.
Grind out or drill slots as appropriate to accommodate Helifix reinforcements.
Vacuum out drill holes to remove any dust traces.
Grout in reinforcement leaving neat joint.
Install 55 x Helifix Cem Ties to the identified areas at approximately 1LM lengths as per manufacturers recommendations (Helifix PW02).
Fill gaps using epoxy mortar, this will re-secure the area.
For the internal crack stitching and repairing, rake out the mortar joints, flush out and well wet joints to introduce 6 x Helifix Cem Ties as per manufacturers recommendations (Helifix RF08).
Upon completion, re-point gable in a mortar mix to match existing as close as possible.
Carry out resin injection using a thixotropic epoxy resin to the vertical crack to existing internal random stonework - up to 1LM.
Remove all debris into appropriately marked location to ensure compliance with ‘Duty of Care’ regulations leaving working area in safe condition.
STATUS: Principal contractor
Previous page: Contact Us
Reconstituted Stone | Terracotta and Faience Restoration | Timber Repair | Epoxy Resin Injection
Concrete Repair | Structural Repair | Waterproof Deck Membranes | Damp Proofing
Basement Waterproofing (Tanking Membranes) | Pest Control | Helifix | K-grip
Car Park Refurbishment